CAPM Practice Question

As a project manager, you discover that a team member has mistakenly over-reported the project's progress to the client, making it seem more advanced than it actually is. Which action should you take that best aligns with the PMI Code of Ethics and Professional Conduct?

  • Allow the current report to stand to maintain client confidence and work internally to align progress with the reported status.

  • Reassign the team member to a different role to prevent similar mistakes in future reports.

  • Inform the client about the discrepancy and provide the accurate project status.

  • Discuss the issue with the team member privately and correct the report before sending future updates.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot