As a project manager, you discover that a team member has intentionally falsified test results to meet a project deadline. According to the PMI Code of Ethics and Professional Conduct, what is the most appropriate action for you to take?

  • Remove the team member from the project

  • Confront the team member privately before involving others

  • Report the issue at the end of the project to to keep on schedule

  • Report the team member's actions to appropriate management and take corrective action

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot