The minimum time to complete the project is 10 weeks.
We identify the critical paths—longest duration paths through the project:
Path A-B-D-F:
A (2 weeks) âž” B (3 weeks) âž” D (2 weeks) âž” F (3 weeks)
Total duration: 2 + 3 + 2 + 3 = 10 weeks
Path A-C-E-F:
A (2 weeks) âž” C (4 weeks) âž” E (1 week) âž” F (3 weeks)
Total duration: 2 + 4 + 1 + 3 = 10 weeks
Since Activity F depends on both D and E, and both paths take 7 weeks before F can start, the earliest completion is at 10 weeks.
Other options are incorrect due to miscalculations or overlooking dependencies.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a critical path in project management?
Open an interactive chat with Bash
What does it mean when multiple critical paths have the same duration?
Open an interactive chat with Bash
How do you calculate the total duration of a path in a project network?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .