CAPM Practice Question
As a project manager, you are planning a project with the following activities, durations (in weeks), and dependencies:
- Activity A: Duration 2 weeks, no dependencies
- Activity B: Duration 3 weeks, depends on Activity A
- Activity C: Duration 4 weeks, depends on Activity A
- Activity D: Duration 2 weeks, depends on Activity B
- Activity E: Duration 1 week, depends on Activity C
- Activity F: Duration 3 weeks, depends on Activities D and E
What is the minimum time required to complete the project?
9 weeks
11 weeks
10 weeks
8 weeks