CAPM Practice Question
As a project manager overseeing the implementation of a new company-wide software system, how can you use this project to act as a vehicle for change within the organization?
By focusing on technical deployment without involving other departments.
By ensuring the new system replicates the current workflows to minimize change.
By reducing user training to optimize project costs and time.
By involving stakeholders to review and improve existing processes during implementation.