As a project manager in a predictive, plan-based project, you are documenting project controls to monitor and manage project performance. Which of the following project artifacts is BEST suited for this purpose?
The Project Management Plan is the primary artifact that outlines how the project will be executed, monitored, and controlled. It includes various subsidiary plans and baselines essential for project control processes. While the Project Charter provides high-level information and authorizes the project, it does not detail control mechanisms. The Issue Log records issues encountered but does not document control procedures. The Risk Register lists identified risks but does not encompass all project controls.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What components are typically included in a Project Management Plan?
Open an interactive chat with Bash
How does the Project Charter differ from the Project Management Plan?
Open an interactive chat with Bash
What is the difference between an Issue Log and a Risk Register?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access