CAPM Practice Question
As a project manager for a construction project, you learn that a new environmental regulation could affect your project's operations. How should you use the stakeholder register to address this situation?
Consult the stakeholder register to identify and engage stakeholders related to environmental compliance
Revise the project scope to accommodate compliance with the new regulation
Update the risk register to include the new environmental regulation as a potential risk
Adjust the project schedule to allow time for implementing necessary changes