CAPM Practice Question

As a project manager for a construction project, you learn that a new environmental regulation could affect your project's operations. How should you use the stakeholder register to address this situation?

  • Consult the stakeholder register to identify and engage stakeholders related to environmental compliance

  • Revise the project scope to accommodate compliance with the new regulation

  • Update the risk register to include the new environmental regulation as a potential risk

  • Adjust the project schedule to allow time for implementing necessary changes

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot