As a business analyst evaluating the project's readiness for delivery, which of the following would BEST indicate that the product meets all specified requirements?
The development team has finished coding all features.
Additional budget has been allocated for future enhancements.
Stakeholders have approved the final project timeline.
All requirements have been traced to passed test cases.
When all documented requirements have been traced to successful test cases, it indicates that every requirement has been verified through testing and meets the acceptance criteria. This demonstrates that the product is ready for delivery. Simply completing coding tasks does not ensure that the requirements are met or that the product functions as intended. Approval of the project schedule does not reflect the fulfillment of requirements. Securing additional funding is unrelated to the product's readiness for delivery.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are test cases in the context of project requirements?
Open an interactive chat with Bash
What does it mean for requirements to be traced?
Open an interactive chat with Bash
Why is stakeholder approval of the project timeline not sufficient for readiness?
Open an interactive chat with Bash
CAPM
Business Analysis Frameworks
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access