CAPM Practice Question
An organization is undertaking a project to produce a routine product with established processes and clear requirements. The project environment is stable, and stakeholders do not anticipate significant changes. Which project management approach would be most appropriate for this project?
Iterative approach allowing for feedback loops
Hybrid approach combining predictive and agile methods
Predictive, plan-based approach
Agile approach focused on flexibility