Adaptive iteration planning replaces the hierarchical task structure of a traditional WBS by organizing work into prioritized iterations.
True
False
Adaptive iteration planning replaces the hierarchical task structure of a traditional WBS by organizing work into prioritized iterations.
True
False
This statement is True. In adaptive project management, the hierarchical Work Breakdown Structure (WBS) of traditional approaches is replaced with iterations that prioritize and organize tasks based on value and adaptability. Work is planned in cycles or sprints, focusing on delivering functional increments rather than following a fixed hierarchy.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.