CAPM Practice Question
According to the PMBOK Guide, in which project management process group does the Collect Requirements process occur?
Executing
Monitoring and Controlling
Planning
Initiating
According to the PMBOK Guide, in which project management process group does the Collect Requirements process occur?
Executing
Monitoring and Controlling
Planning
Initiating
Collect Requirements is part of the Planning process group. During Planning, the project team gathers and documents stakeholder needs that will shape the scope baseline. The Executing process group focuses on carrying out the approved plan; therefore, Collect Requirements is completed before execution begins.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.