A Scrum team is preparing to plan the next sprint and needs to decide what work to include. What should they use as the primary input to determine the scope of the upcoming sprint?
The technical specifications document created during project initiation.
A detailed work breakdown structure prepared by the project manager.
The list of priority items provided by the product owner, called a product backlog.
In Scrum, the team uses the list of priority items provided by the product owner, known as the product backlog, as the primary input for sprint planning. The team selects items from the top of this prioritized list based on their capacity. A detailed work breakdown structure (WBS) and Gantt chart are tools from predictive methodologies and are not typically used in agile projects. Technical specifications from project initiation may not reflect the current priorities and are less relevant for sprint planning.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a product backlog in Scrum?
Open an interactive chat with Bash
How does the team determine how many items to pull from the product backlog?
Open an interactive chat with Bash
Why aren't tools like Gantt charts or the WBS used in Scrum sprint planning?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .