A project team is using an adaptive approach for a new software development project. The product backlog contains numerous features and tasks. What is the most effective guiding principle for ordering the work in the backlog?
Prioritize tasks with the lowest effort to complete them first
Prioritize tasks based on the business value they deliver to stakeholders
Prioritize tasks as requested by the lead developer
Prioritize tasks based on the technical dependencies between them
In adaptive project management, the primary driver for task prioritization is the value delivered to the customer or stakeholders. Focusing on high-value items first ensures the most important features are delivered early, maximizing return on investment and allowing for crucial feedback. While task effort, dependencies, and team input are considerations, they are secondary to delivering value.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
How is 'value delivered to the customer' determined in adaptive project management?
Open an interactive chat with Bash
What are some techniques for prioritizing tasks in adaptive project management?
Open an interactive chat with Bash
Why is feedback important in adaptive project management?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access