CAPM Practice Question
A project's earned value (EV) is $80,000, and its planned value (PV) is $100,000. Based on these values, how is the project performing relative to its schedule?
The project is behind schedule by $20,000.
The project is on schedule with no variance.
The project is behind schedule by $180,000.
The project is ahead of schedule by $20,000.