CAPM Practice Question
A project's earned value (EV) is $12,000 and its planned value (PV) is $15,000. What is the result of subtracting PV from EV for this project?
$27,000
$0
$3,000
-$3,000
A project's earned value (EV) is $12,000 and its planned value (PV) is $15,000. What is the result of subtracting PV from EV for this project?
$27,000
$0
$3,000
-$3,000
Subtracting the planned value (PV) from the earned value (EV) gives EV - PV = $12,000 - $15,000 = -$3,000. Therefore, the correct answer is -$3,000. The option $3,000 is incorrect because it ignores the negative sign, which is important in indicating whether the project is ahead or behind schedule. $27,000 is incorrect because it results from adding EV and PV rather than subtracting. $0 is incorrect because EV and PV are not equal.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.