CAPM Practice Question

A project manager working on a predictive, plan-based software development project needs to report schedule variance (SV) at the next status meeting to show whether the team is ahead of or behind the approved schedule baseline. Which project performance measurement technique should the manager use to calculate SV?

  • Resource Leveling

  • Earned Value Management

  • Risk Analysis

  • Critical Path Method

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot