A project manager needs to determine the sequence of activities that directly affects the project's finish date. Which technique should be used to identify these critical tasks?
The Critical Path Method is used to identify the longest sequence of activities in a project plan which must be completed on time for the project to complete on schedule. It highlights tasks that cannot be delayed without affecting the project's finish date. Resource Leveling adjusts the schedule based on resource constraints but doesn't identify critical tasks. A Gantt Chart visually represents the schedule but doesn't inherently highlight the critical path. Earned Value Analysis assesses project performance and progress but doesn't focus on sequencing of critical activities.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Critical Path Method (CPM)?
Open an interactive chat with Bash
How do you identify tasks in the critical path?
Open an interactive chat with Bash
What are the implications of tasks on the critical path?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access