CAPM Practice Question

A project manager must choose a development life cycle for a new highway bridge. The engineering design is complete, regulatory approvals are in place, and no scope changes are expected. Which project characteristic most strongly indicates that a predictive, plan-based (waterfall) life cycle is appropriate?

  • Requirements and scope are clearly defined, stable, and unlikely to change.

  • The customer expects usable portions of the bridge to be delivered every two weeks.

  • The team must experiment with new materials, and requirements are expected to evolve.

  • Stakeholder priorities shift frequently, creating a high-uncertainty environment.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot