CAPM Practice Question
A project manager is reviewing the schedule and notices a sequence of tasks that dictates the earliest possible completion date of the project. One of these tasks is delayed due to unforeseen circumstances. What is the MOST appropriate action for the project manager to take?
Reallocate resources from other tasks to mitigate the delay.
Apply Earned Value Management to monitor the project's progress.
Proceed without changes as the delay will not affect the project completion date.
Use the Critical Path Method to assess the impact of the delay on the project schedule.