CAPM Practice Question

A project manager is reviewing the schedule and notices a sequence of tasks that dictates the earliest possible completion date of the project. One of these tasks is delayed due to unforeseen circumstances. What is the MOST appropriate action for the project manager to take?

  • Reallocate resources from other tasks to mitigate the delay.

  • Apply Earned Value Management to monitor the project's progress.

  • Proceed without changes as the delay will not affect the project completion date.

  • Use the Critical Path Method to assess the impact of the delay on the project schedule.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot