CAPM Practice Question

A project manager is reviewing the project's performance using earned value analysis. The Planned Value (PV) for a specific period is $25,000, and the Earned Value (EV) is $20,000. What is the Schedule Variance (SV) and what does it indicate about the project's progress?

  • The SV is -$5,000, and the project is over budget.

  • The SV is +$5,000, and the project is under budget.

  • The SV is -$5,000, and the project is behind schedule.

  • The SV is +$5,000, and the project is ahead of schedule.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot