CAPM Practice Question
A project manager is reviewing the following data: Earned Value (EV) is $10,000, Actual Cost (AC) is $12,000, and Planned Value (PV) is $11,000. Based on these figures, which statement best describes the project's performance?
The project is under budget and behind schedule.
The project is over budget and behind schedule.
The project is over budget but ahead of schedule.
The project is under budget and ahead of schedule.