A project manager is overseeing a project with a fixed budget of $500,000 and a specified completion date in six months. The project team assumes that critical resources will be available when needed. During execution, a key team member resigns, causing delays in tasks. Additionally, regulatory changes now require additional compliance steps that the project must address. Which of the following is an example of the most immediate issue in this scenario?
An issue is a current problem that is adversely impacting the project. In this scenario, delays due to a team member resigning are an issue because it is a present problem affecting the project's execution. The project's limited budget and schedule are constraints, which are fixed limitations the project must adhere to. The assumption that critical resources will be available is an assumption made during planning. Regulatory changes requiring additional compliance steps are also an issue, but since only one option can be selected, delays due to the team member's resignation is the most immediate issue impacting tasks.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are project constraints?
Open an interactive chat with Bash
What are some common causes of project delays?
Open an interactive chat with Bash
What is the importance of resource availability in project management?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access