A project manager is overseeing a project with a fixed budget of $500,000 and a specified completion date in six months. The project team assumes that critical resources will be available when needed. During execution, a key team member resigns, causing delays in tasks. Additionally, regulatory changes now require additional compliance steps that the project must address. Which of the following is an example of the most immediate issue in this scenario?
Delays due to a team member resigning.
Assuming critical resources will be available when needed.
The project's limited budget and completion date.
Regulatory changes requiring additional compliance steps.