A project manager is overseeing a complex project involving multiple teams and stakeholders. During execution, the client asks for a significant modification to the project scope. What should the project manager do first to ensure proper integration of this modification into the project?

  • Evaluate the impact of the modification on project objectives and follow the project's change control process

  • Implement the modification to meet the client's needs

  • Adjust the project schedule and budget to accommodate the scope modification

  • Update the project management plan to reflect the requested modification

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot