CAPM Practice Question
A project manager is overseeing a complex project involving multiple teams and stakeholders. During execution, the client asks for a significant modification to the project scope. What should the project manager do first to ensure proper integration of this modification into the project?
Evaluate the impact of the modification on project objectives and follow the project's change control process
Implement the modification to meet the client's needs
Adjust the project schedule and budget to accommodate the scope modification
Update the project management plan to reflect the requested modification