CAPM Practice Question

A project manager is leading a complex project and needs to organize the project scope into manageable sections to enhance planning, execution, and control. Which of the following should the project manager create?

  • Build a Requirements Traceability Matrix

  • Develop a Work Breakdown Structure

  • Prepare a Cost Breakdown Structure

  • Create a Project Schedule Network Diagram