CAPM Practice Question

A project manager is in the execution phase of a predictive, plan-based project. To ensure the project's deliverables will meet the standards defined in the quality management plan, which of the following practices is most appropriate for the project team to apply?

  • Delegating the responsibility for all quality planning to individual team members.

  • Limiting quality measurements to the final deliverable acceptance testing.

  • Adjusting quality standards as the project progresses without updating the plan.

  • Incorporating continuous process improvement activities throughout the project lifecycle.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot