CAPM Practice Question
A project manager is examining the project scope statement. What should be included to clearly define what is not included in the project work?
Project objectives
Project deliverables
Assumptions
Project exclusions
A project manager is examining the project scope statement. What should be included to clearly define what is not included in the project work?
Project objectives
Project deliverables
Assumptions
Project exclusions
Project exclusions are essential in the project scope statement as they specify what is outside the project's boundaries. This helps manage stakeholder expectations and prevent scope creep by clarifying any work or deliverables that are not part of the project. Project deliverables and objectives outline what the project aims to produce and achieve, while assumptions are conditions considered to be true for planning purposes; none of these specify what is excluded from the project.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.