A project manager is compiling documentation that will guide the execution and control of a newly initiated project. Which of the following is a deliverable of the project management plan rather than the product management plan?
The risk management plan is a component of the project management plan. It details how risk management activities will be structured and performed throughout the project, focusing on identifying, analyzing, and responding to project risks. In contrast, the product design specifications, user experience requirements, and market analysis report are deliverables of the product management plan, as they pertain to the product's features, user expectations, and market considerations.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the purpose of a risk management plan in project management?
Open an interactive chat with Bash
How does a project management plan differ from a product management plan?
Open an interactive chat with Bash
Why aren’t product design specifications included in the project management plan?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .