CAPM Practice Question

A project manager is assigned to lead a project with stable and well-understood requirements. Stakeholders require a comprehensive plan, detailed schedule, and cost estimates before the project begins, and minimal changes are expected during execution. Which project management approach is most suitable for this project?

  • Iterative approach

  • Adaptive approach

  • Incremental approach

  • Predictive approach

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot