CAPM Practice Question
A project manager finds that the project has an earned value (EV) of $120,000 and a planned value (PV) of $150,000 at a certain point in time. What does this tell the project manager about the project's schedule performance?
The project is ahead of schedule by $30,000.
The project is on schedule.
The project is behind schedule by $30,000.
The project is over budget by $30,000.