A project manager discovers that unapproved changes have been made to the project scope, causing conflicts among project objectives and impacting the schedule and budget. What should the project manager do to best address this issue?
Implement the change control process to approve the changes retroactively.
Examine the integration management processes to evaluate the impact and coordinate a response.
Adjust the project management plan to incorporate the changes and inform stakeholders of the updates.
Direct the team to revert the changes and proceed according to the original plan.
By examining the integration management processes, the project manager can evaluate the overall impact of the unapproved changes on all aspects of the project and coordinate appropriate corrective actions. Integration management ensures that all elements of the project are properly coordinated and that changes are managed holistically.
Adjusting the project management plan without a thorough evaluation may overlook critical impacts on other areas. Implementing the change control process retroactively does not resolve the conflicts already caused by the changes. Directing the team to revert the changes without analysis may lead to further issues or resistance from the team.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is integration management in project management?
Open an interactive chat with Bash
Why is retroactively approving changes not recommended?
Open an interactive chat with Bash
What is the importance of evaluating unapproved changes before taking corrective action?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .