CAPM Practice Question

A project manager creating a schedule needs to identify the sequence of dependent tasks that represents the longest path through the project. This specific sequence dictates the shortest possible time in which the project can be completed. What is this sequence called?

  • Critical path

  • Resource leveling

  • Gantt chart

  • Work breakdown structure