A project manager anticipates that a new regulatory policy might affect the project's timeline. Which document should the project manager update to record this potential impact?
The project manager should update the risk register to document the anticipated effect of the new regulatory policy on the project's timeline. The risk register is utilized to capture all potential risks, their analysis, and planned responses. The change log is meant for tracking approved changes to project baselines, the issue log records current problems that need immediate attention, and the lessons learned register captures insights gained from project experiences.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a risk register in project management?
Open an interactive chat with Bash
How is a risk register different from an issue log?
Open an interactive chat with Bash
Why is the change log not used to document potential risks?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .