CompTIA Project+ PK0-005 Practice Question
While working on a project, the project manager identifies a supplier risk due to the supplier's unstable financial condition. To handle this, the manager decides to work with multiple suppliers instead of relying on a single one. Which risk response is being applied?
Transfer
Mitigate
Avoid
Accept