Testing cannot begin until development is finished, so the sequence is inherent in the nature of the work-making it a mandatory (hard-logic) dependency. Because both activities are executed by teams within the organization, it is also internal. Taken together, the relationship is classified as a mandatory-internal dependency. The other options are incorrect because they either involve an external party or represent discretionary (soft-logic) choices that are not inherent in the work.