CompTIA Project+ PK0-005 (V5) Practice Question

While building your schedule, you identify the following relationship:

  • Task A: Develop a new product feature (performed by your project team)
  • Task B: Test the new feature (also performed by your project team)

Task B cannot start until Task A has been completed.

From the standpoint of dependency attributes, which classification most accurately describes the relationship between Task A and Task B?

  • Mandatory-internal dependency

  • Discretionary-external dependency

  • Mandatory-external dependency

  • Discretionary-internal dependency

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot