Which of the following is the most effective method for a project manager to provide constructive feedback to an individual team member?
Provide feedback during a team meeting so others can learn from it
Wait until the annual performance review to provide feedback
Schedule a one-on-one meeting with the team member to discuss their performance
Send an email to the team member outlining the feedback