CompTIA Project+ PK0-005 (V5) Practice Question

Which of the following BEST describes a project milestone?

  • A mandatory dependency that links the end of one phase to the start of another.

  • A collection of related tasks that, when completed, form a major deliverable.

  • A short-duration task that requires minimal resources to complete.

  • A significant point or event in the project with zero duration and no resource consumption.

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot