A milestone is a significant point or event in a project schedule, such as the completion of a major phase or deliverable. It is represented as a zero-duration event and does not consume resources itself. Its purpose is to serve as a checkpoint for tracking progress. The other options are incorrect. Tasks, even short ones, have a duration and consume resources. A collection of tasks describes a summary task or work package. A dependency is a relationship between tasks, not a point in time.