Which document is used to track problems that arise during a project, ensuring they are addressed and resolved?
Risk register
Issue log
Project dashboard
Change log
Which document is used to track problems that arise during a project, ensuring they are addressed and resolved?
Risk register
Issue log
Project dashboard
Change log
An issue log is a document used to track problems that occur during a project. It helps project managers identify, monitor, and resolve issues promptly to keep the project on track. The change log records alterations to the project scope or plans. The risk register lists potential risks that might affect the project in the future. The project dashboard provides a high-level overview of the project's status and performance metrics.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Information Technology Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All Information Technology Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.