CompTIA Project+ PK0-005 (V5) Practice Question

What is one key challenge in managing change control for cloud services that is less prevalent with on-premises systems?

  • Managing internal approval processes for changes.

  • Documenting changes for internal audit purposes.

  • Coordinating change schedules with external service providers.

  • Ensuring hardware compatibility with new updates.

CompTIA Project+ PK0-005 (V5)
Basics of IT and Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot