After a change has been approved and the project plan updated, the next step is for the project team to implement the changes. This involves performing the necessary work to modify project deliverables as specified. 'Validate the change implementation' comes after implementation, where the change is reviewed for effectiveness. 'Conduct impact assessments' is done before approval to understand the implications of the change. 'Document change recommendations' is part of proposing the change, not executing it.