In a software change control process, which of the following is the MOST important consideration during the risk assessment phase?

  • Notifying customers about the upcoming change

  • Calculating the cost of new software licenses

  • Evaluating the impact of the change on current operations

  • Scheduling the maintenance window to minimize disruption

CompTIA Project+ PK0-005 (V5)
Basics of IT and Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot