CompTIA Project+ PK0-005 Practice Question

During the project execution phase, what activity involves regularly evaluating a vendor's work to ensure it meets project requirements?

  • You selected this option

    Resource allocation

  • You selected this option

    Developing a communication plan

  • You selected this option

    Risk assessment

  • You selected this option

    Monitoring performance