CompTIA Project+ PK0-005 Practice Question
During the planning phase of a project, a project manager needs to determine the critical path for the project schedule. Which of the following tools would BEST help in accomplishing this task?
Milestone chart
Budget burndown chart
Project network diagram
Gantt chart