CompTIA Project+ PK0-005 Practice Question
During the initiation phase of a project, you are responsible for developing a records management plan for project documents. What is one key benefit of effectively managing project documents in this plan?
It ensures project documents are organized and accessible to authorized stakeholders.
It establishes quality assurance procedures for project deliverables.
It outlines procurement processes for acquiring project resources.
It defines team roles and responsibilities for task execution.