During the initiation phase of a project, what is the BEST way for a project manager to assess the level of impact and engagement of the project's stakeholders?
Create a stakeholder register that lists all stakeholders and their contact information.
Send a survey to stakeholders asking about their expectations.
Hold a kickoff meeting to introduce the project to stakeholders.
Conduct a stakeholder analysis to evaluate their power and interest.
Conducting a stakeholder analysis is the best method to assess stakeholders' level of impact and engagement. It involves evaluating each stakeholder's power and interest in the project, allowing the project manager to develop appropriate strategies for stakeholder management. Creating a stakeholder register is important for documenting stakeholder information but does not assess their impact and engagement levels. Sending a survey may gather stakeholder expectations but might not accurately determine their power and interest. Holding a kickoff meeting introduces the project but does not provide an assessment of stakeholders' influence on the project.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is stakeholder analysis in project management?
Open an interactive chat with Bash
How does a stakeholder register differ from a stakeholder analysis?
Open an interactive chat with Bash
Why is the power-interest grid important in stakeholder analysis?