CompTIA Project+ PK0-005 (V5) Practice Question

During the initiation phase of a project, the project manager needs to establish how project documents and data will be managed, including who has permission to view and modify them. Which of the following is the BEST way to formally define and control these permissions?

  • Grant document access when assigning tasks

  • Assign roles and responsibilities in the RACI matrix

  • Specify communication methods in the communication plan

  • Document permissions in the records management plan

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot