CompTIA Project+ PK0-005 Practice Question
During the initiation phase, a project manager needs to define the project's inclusions and exclusions to set clear boundaries. Which document should the project manager create to achieve this?
Preliminary scope statement
Risk management plan
Communication plan
Project charter