During the execution phase of a project, a vendor is consistently missing delivery deadlines, affecting the project timeline. As the project manager, what is the BEST action to take to enforce the vendor's rules of engagement?

  • Initiate a formal performance review with the vendor to address the delays.

  • Replace the vendor with a new one who can meet the schedule.

  • Allow the vendor more time to deliver to avoid conflict.

  • Report the vendor's non-compliance to upper management before communicating with the vendor.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot