During the execution phase of a project, a team member suggests a beneficial change that could improve the project's deliverable. What should the project manager do first?
Evaluate the change's impact on project scope, schedule, and cost
Reject the change to prevent scope creep
Implement the change to take advantage of the improvement
Forward the suggestion to senior management for approval