During the execution phase, a project team identifies a more efficient method for a planned task. The project manager initiates the formal change control process, and the change is approved. What should the project manager do NEXT?

  • Direct the team to implement the new method immediately to gain efficiency.

  • Adhere to the original plan to avoid any deviation during the execution phase.

  • Update the project management plan to incorporate the change, then direct the team to proceed with the new method.

  • Ask the project sponsor for a final review before implementing the approved change.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot