CompTIA Project+ PK0-005 (V5) Practice Question

During the discovery phase of an IT infrastructure-upgrade project, you learn that the customer already has active contracts for hardware maintenance and software licensing covering some components you intend to replace. Which action should you take to ensure these agreements are properly handled in your project plan?

  • Request that procurement terminate the existing contracts and issue new agreements that align with the project's requirements

  • Conduct a detailed contract analysis with procurement and legal to map obligations, constraints, and dependencies into the project scope, schedule, and risk register

  • Proceed with planning as usual and assume the project sponsor will address any conflicts that arise from the contracts

  • Defer consideration of the existing contracts until the execution phase to avoid delaying the planning timeline

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot